ANDRITZ HYDRO CORP
CHARLOTTE, North Carolina
Total Received
$533.5M
Total Awards
24
State
North Carolina
Last Updated
Apr 21, 2026
Yearly Funding Trend
$530.9M24
$2.6M25
Top 24 Awards to ANDRITZ HYDRO CORP
Largest individual federal awards on record for this recipient, ranked by obligated amount. Data through April 21, 2026.
| Award | Awarding Agency | Program | Place | FY | Obligation |
|---|---|---|---|---|---|
CONT_AWD_INR11PC10020_1425_-NONE-_-NONE- MODIFICATION P00286 IS AN ADMINISTRATIVE MODIFICATION TO DEOBLIGATE ALL REMAINING FUNDS TO PREPARE FOR CONTRACT CLOSE OUT. | Department of the Interior Bureau of Reclamation | — | GRAND COULEE, WA-05 | 2024 | $149,281,132 |
CONT_AWD_W912BV21C0014_9700_-NONE-_-NONE- DESCOPE OIL PURIFICATION SYSTEM | Department of Defense Department of the Army | — | SALLISAW, OK-02 | 2024 | $91,540,766 |
CONT_AWD_W912P523C0002_9700_-NONE-_-NONE- ADDING PAYMENT PROCEDURES FOR OFF-SITE MATERIALS. | Department of Defense Department of the Army | — | HENDERSONVILLE, TN-06 | 2024 | $82,545,748 |
CONT_AWD_W912P520C0018_9700_-NONE-_-NONE- EXERCISE OPTIONAL CLINS 0192, 0302, 0408 | Department of Defense Department of the Army | — | KUTTAWA, KY-01 | 2024 | $77,694,830 |
CONT_AWD_140R1019C0008_1425_-NONE-_-NONE- THE PURPOSE OF THIS MODIFICATION IS TO ENSURE COMPLIANCE WITH UPDATED FEDERAL GUIDANCE AND TO ELIMINATE NON-STATUTORY SUSTAINABILITY REQUIREMENTS, AS WELL AS ENHANCE THE REPRESENT… | Department of the Interior Bureau of Reclamation | — | GRAND COULEE, WA-05 | 2024 | $33,979,078 |
CONT_AWD_W9127N16C0028_9700_-NONE-_-NONE- UNIT 14 OPTION AWARDS | Department of Defense Department of the Army | — | RUFUS, OR-02 | 2024 | $21,272,592 |
CONT_AWD_140R1023C0004_1425_-NONE-_-NONE- CHANGE ORDER P00009 SERVO MOTORS. | Department of the Interior Bureau of Reclamation | — | MOUNTAIN HOME, ID-02 | 2024 | $16,342,675 |
CONT_AWD_W9127S21C0006_9700_-NONE-_-NONE- CONTRACT FOR FY21 BV UNITS1-2 GENERATOR STATOR REWIND. REFERENCE NO. R00012 CC014 THRUST TUB MODIFICATION | Department of Defense Department of the Army | — | EUREKA SPRINGS, AR-03 | 2024 | $15,929,800 |
CONT_AWD_W912EF21C0012_9700_-NONE-_-NONE- REASSEMBLE GENERATING UNIT | Department of Defense Department of the Army | — | UMATILLA, OR-02 | 2024 | $14,732,853 |
CONT_AWD_W912BV21C0007_9700_-NONE-_-NONE- DEFINITIZE U2 STATOR & ROTOR ABATEMENT | Department of Defense Department of the Army | — | SAND SPRINGS, OK-01 | 2024 | $11,133,839 |
CONT_AWD_W9127S11C0001_9700_-NONE-_-NONE- U3 GGB FLAME SPRAY | Department of Defense Department of the Army | — | WEBBERS FALLS, OK-02 | 2024 | $6,051,849 |
CONT_AWD_140R3021F0034_1425_140R3019D0013_1425 A9 TURBINE OVERHAUL - MODIFICATION P00006 ADDS AND FULLY FUNDS CHANGE ORDERS, EXTENDS PERIOD OF PERFORMANCE | Department of the Interior Bureau of Reclamation | — | SPOKANE VALLEY, WA-05 | 2024 | $2,710,595 |
CONT_AWD_140R6024F0025_1425_140R6021D0003_1425 MT-CF POWERPLANT GENERATOR TASK ORDER 3 | Department of the Interior Bureau of Reclamation | — | HELENA, MT-02 | 2024 | $1,898,300 |
CONT_AWD_140R6023F0005_1425_140R6021D0003_1425 TASK ORDER - INSTALLATION AND FIELD TESTING OF THE GENERATOR STATOR CORE AND ARMATURE WINDING | Department of the Interior Bureau of Reclamation | — | HELENA, MT-02 | 2024 | $1,863,000 |
CONT_AWD_140R3023F0087_1425_140R3019D0013_1425 THE PURPOSE OF THIS MODIFICATION IS TO ENSURE COMPLIANCE WITH UPDATED FEDERAL GUIDANCE AND TO ELIMINATE NON-STATUTORY SUSTAINABILITY REQUIREMENTS, AS WELL AS ENHANCE THE REPRESENT… | Department of the Interior Bureau of Reclamation | — | BOULDER CITY, NV-01 | 2025 | $1,501,652 |
CONT_AWD_140R6020C0023_1425_-NONE-_-NONE- THE PURPOSE IS TO MODIFY IS TO DESCOPE UNIT #2 SHAFT SEAL REPLACEMENT REQUIREMENTS IAW SPECIFICATION CHANGES. | Department of the Interior Bureau of Reclamation | — | TWIN LAKES, CO-07 | 2024 | $1,443,739 |
CONT_AWD_140R3022F0064_1425_140R3019D0013_1425 THE PURPOSE OF THIS MODIFICATION IS TO ENSURE COMPLIANCE WITH UPDATED FEDERAL GUIDANCE AND TO ELIMINATE NON-STATUTORY SUSTAINABILITY REQUIREMENTS, AS WELL AS ENHANCE THE REPRESENT… | Department of the Interior Bureau of Reclamation | — | BOULDER CITY, NV-01 | 2025 | $1,118,077 |
CONT_AWD_140R3024F0089_1425_140R3019D0013_1425 HOOVER DAM GENERATING UNIT A5 RE-WEDGE | Department of the Interior Bureau of Reclamation | — | BOULDER CITY, NV-01 | 2024 | $1,013,470 |
CONT_AWD_140R3023F0049_1425_140R3019D0013_1425 FABRICATION AND DELIVERY OF A DRAFT TUBE BULKHEAD | Department of the Interior Bureau of Reclamation | — | BOULDER CITY, NV-01 | 2024 | $919,708 |
CONT_AWD_140R3024F0092_1425_140R3019D0013_1425 BUSHINGS FOR KA3A KA5A GSU TRANSFORMERS - POP EXTENSION | Department of the Interior Bureau of Reclamation | — | BOULDER CITY, NV-01 | 2024 | $464,725 |
CONT_AWD_140R3024F0005_1425_140R3019D0013_1425 DAVIS D3 GENERATOR THRUST BEARING SPRINGS | Department of the Interior Bureau of Reclamation | — | BULLHEAD CITY, AZ-09 | 2024 | $67,385 |
CONT_AWD_W9127824P0024_9700_-NONE-_-NONE- REPAIR OF CP-6003 MASTER CONTROL UNIT | Department of Defense Department of the Army | — | BUFORD, GA-09 | 2024 | $19,940 |
CONT_IDV_140R6021D0003_1425 CANYON FERRY POWERPLANT GENERATOR REWIND REFURBISHMENT - IDIQ | Department of the Interior Bureau of Reclamation | — | — | 2024 | $0 |
CONT_IDV_140R6025D0003_1425 MTE PUMP GENERATING MANUFACTURING AND REHABILITATION MULTIPLE AWARD IDIQ | Department of the Interior Bureau of Reclamation | — | — | 2025 | $0 |
Top 24 awards shown, ranked by obligated amount. Dates reflect performance period; last-modified dates match USAspending.gov. Complete listings include all transaction history going back to FY2024.
Industries
View All→123456
OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION$494.9M
MOTOR AND GENERATOR MANUFACTURING$15.9M
POWER AND COMMUNICATION LINE AND RELATED STRUCTURES CONSTRUCTION$11.1M
TURBINE AND TURBINE GENERATOR SET UNITS MANUFACTURING$7.8M
ALL OTHER SPECIALTY TRADE CONTRACTORS$3.8M
HYDROELECTRIC POWER GENERATION$20K